Irrigation Scheduling Calculator

Build a full irrigation schedule: net depth per irrigation from total available water and allowed depletion, the interval from crop ET, gross depth from system efficiency, and run time.

Your site and system

Results update as you type and as you choose your soil and system below.

Units
Soil texture (available water capacity) Required

Based on UC ANR's AWC-by-texture guidance, or from a soil test or NRCS Web Soil Survey.

in

The effective rooting depth for what you're irrigating — commonly 6-12 in (15-30 cm) for turf and vegetables, more for shrubs and trees.

%

50% is a common default. Why 50%.

in/day

ETc = reference ET (ETo) × crop coefficient (Kc), per the FAO-56 method. Look up ETo from your state's ag-weather network and Kc for your crop.

Irrigation system efficiency Required

Typical values from California's landscape water ordinance worksheet.

in/hr

From a catch-can test for sprinklers, or your drip system's precipitation rate.

Your irrigation schedule

Based only on the values you enter.

Enter your soil, root depth, ETc, efficiency and application rate to see:

  • net and gross depth per irrigation
  • how many days between irrigations
  • run time, and a suggested schedule

The four steps of an irrigation schedule

A complete irrigation schedule answers four questions in sequence, following the standard soil-water-budget approach used in irrigation water management planning: how much water to apply, how often, how much to actually run the system to deliver that, and how long to run it.

The four steps this calculator chains together.
StepAnswersDepends on
1. Net depthHow much water refills the allowed deficitTotal available water (TAW) × allowed depletion (MAD)
2. IntervalHow many days that lastsNet depth ÷ crop water use (ETc)
3. Gross depthHow much to actually apply, accounting for lossesNet depth ÷ system efficiency
4. Run timeHow long to run the systemGross depth ÷ application rate

If you only need the interval on its own, the irrigation interval calculator covers just that step. For a day-by-day running water balance that tracks actual rainfall and changing ET over time, see the soil water balance calculator instead; this calculator produces one fixed schedule rather than a daily ledger.

How this irrigation scheduling calculator works

1. Total available water (TAW)

Available water capacity (AWC) is how much water a soil holds per foot of depth for plants to draw on. University of California Agriculture and Natural Resources gives typical ranges of about 0.5-1.0 in/ft for sand, 1.0-1.5 in/ft for sandy loam, 1.5-2.0 in/ft for silt or clay loam, and 2.0-2.5 in/ft for clay. This calculator uses the middle of the range for the texture you choose, or your own entered value.

TAW

TAW = Root zone depth × (AWC ÷ 12)

2. Net depth per irrigation

North Dakota State University Extension's Checkbook Method of irrigation scheduling starts irrigation once the soil-moisture deficit reaches a set share of TAW, commonly 50%; that share is the management allowed depletion (MAD).

Net depth

Net depth = TAW × MAD

3. Interval, from ETc

Days between irrigations

Interval = Net depth ÷ ETc

Rounded down to a whole number of days, minimum 1, so the schedule doesn't exceed the allowed depletion.

4. Gross depth, using efficiency

No system delivers all its water to the root zone. California's Model Water Efficient Landscape Ordinance worksheet uses 0.75 for spray-head irrigation and 0.81 for drip as typical application efficiencies.

Gross depth

Gross depth = Net depth ÷ Efficiency

5. Run or set time

Run time

Minutes = Gross depth ÷ Application rate × 60

When this calculator isn't the right tool

Use a different approach for:

Irrigation scheduling calculation example

Sandy loam soil (AWC 1.25 in/ft), a 12 in root zone, 50% MAD, ETc of 0.2 in/day, a spray system at 75% efficiency, applying 1.5 in/hr.

  1. TAW: 12 × (1.25 ÷ 12) = 1.25 in.
  2. Net depth: 1.25 × 50% = 0.625 in.
  3. Interval: 0.625 ÷ 0.2 = 3.125 → every 3 days.
  4. Gross depth: 0.625 ÷ 0.75 = 0.833 in.
  5. Run time: 0.833 ÷ 1.5 × 60 ≈ about 33 min.

The same calculation in metric

Sandy loam soil, a 30 cm root zone, 50% MAD, ETc of 5 mm/day, a drip system at 81% efficiency, applying 8 mm/hr:

  1. TAW: 30 × (1.25 ÷ 12) = 3.125 cm.
  2. Net depth: 3.125 × 50% = 1.5625 cm = 15.625 mm.
  3. Interval: 15.625 ÷ 5 = 3.125 → every 3 days, matching the US example.
  4. Gross depth: 15.625 ÷ 0.81 ≈ 19.29 mm.
  5. Run time: 19.29 ÷ 8 × 60 ≈ about 2 hr 25 min.

Both examples use the same formulas the calculator runs; enter your own site's numbers above for your schedule.

Practical guidance

Measure your system's real application rate rather than assuming a manufacturer figure. For sprinklers, run a catch-can test: set several straight-sided containers across the irrigated area, run the system for a set time, and measure the average depth collected to get inches or millimeters per hour. For drip systems, use the manufacturer's rated emitter flow and spacing, then check it against an actual measurement where practical.

If the calculated interval comes out under one day, the net depth this soil and root zone can hold depletes faster than once-daily watering can sensibly deliver at that ETc. Consider a shallower target depth, splitting the gross depth into shorter cycles with soak time between them, or improving distribution uniformity so less water is needed to reach the driest spots.

Check local watering rules. Many water utilities set watering days, hours or restrictions, especially during drought. Where those apply, they take priority over any calculated schedule.

What changes the schedule

Inputs and conditions that shift the resulting schedule, and what to change.
FactorEffectWhat to adjust
Soil texture / AWCCoarser soils hold less water per foot, giving a shorter interval.Use a soil test or Web Soil Survey value where possible.
Root zone depthA deeper effective root zone stores more water and lasts longer.Use the crop's real rooting depth, not a maximum potential depth.
MADA lower allowed depletion shortens the interval and net depth.Lower it for drought-sensitive plantings; extension guidance commonly uses 50% as a general default.
ETc / weatherHot, dry, windy weather raises ETc and shortens the interval.Update ETc regularly rather than using one seasonal figure.
System efficiencyPoor maintenance, wind or mismatched heads lower real-world efficiency below typical values.Audit and maintain the system, or enter a measured efficiency.
RainfallMeaningful rain can reset or delay the next scheduled irrigation.Track rainfall separately and adjust the schedule manually, or use a day-by-day water balance.

Frequently asked questions

What is total available water (TAW) and how is it calculated?

Total available water is the depth of water a soil can hold for plant use within a given root zone depth. It's calculated as available water capacity (AWC), typically expressed as inches of water per foot of soil, multiplied by the root zone depth. University of California Agriculture and Natural Resources gives typical AWC ranges of about 0.5-1.0 in/ft for sandy soils up to 2.0-2.5 in/ft for clay.

What is management allowed depletion (MAD)?

Management allowed depletion is the share of total available water that's allowed to be used up before the next irrigation. North Dakota State University Extension's Checkbook Method of irrigation scheduling keeps the soil-moisture deficit from exceeding 50% of available water capacity before starting irrigation again, which is a widely used default; more drought-sensitive plantings are often managed at a lower depletion.

How is the irrigation interval calculated from ETc?

The interval is the net depth per irrigation divided by the crop's daily water use (ETc), rounded down to a whole number of days. ETc itself follows the FAO-56 approach of multiplying reference evapotranspiration (ETo) by a crop coefficient (Kc) for the specific plant and growth stage.

Why is gross depth higher than net depth?

No irrigation system delivers 100% of the water it uses to the root zone; some is lost to evaporation, wind drift, deep percolation or uneven coverage. Dividing the net depth by the system's application efficiency accounts for that loss. California's Model Water Efficient Landscape Ordinance worksheet uses 0.75 for spray-head irrigation and 0.81 for drip as typical efficiency values.

How do I find my irrigation system's application rate?

Run the system for a measured time and collect the water in several straight-sided containers spread across the area, such as a catch-can test for sprinklers, then measure the depth collected and convert to a rate per hour. Manufacturer specifications for drip emitters and tubing can also give a starting figure to check against a real test.

What root zone depth should I use?

Use the effective rooting depth for what you're irrigating, not the full depth roots could theoretically reach. Shallow-rooted turf and most vegetables are commonly managed on a root zone of roughly 6-12 inches (15-30 cm), while shrubs and trees draw from considerably deeper and wider zones.

Does this calculator track soil moisture day by day?

No. This calculator produces one schedule from a fixed net depth, interval and gross depth, projected forward at a constant rate. For a day-by-day running water balance that adjusts for actual rainfall and changing ET, use the soil water balance calculator instead.

See the soil water balance calculator.

I only need the number of days between waterings. Is there a simpler tool?

Yes. The irrigation interval calculator focuses on just that single step, if you don't need the full net depth, gross depth and run time chain this calculator builds.

See the irrigation interval calculator.

Who built and checked this calculator

Daniel Reeves

Irrigation Design Engineer & Water-Efficiency Specialist

Licensed Professional Engineer and Irrigation Association Certified Irrigation Designer with more than 20 years in irrigation design, system auditing and landscape water management. Full profile

How this page was checked

  • The TAW, net depth, interval, gross depth and run-time math were verified by hand, and both worked examples were traced against the code, including a US/metric cross-check.
  • AWC, MAD and efficiency figures are checked against the extension and ordinance sources below.
  • Every input is validated and every division guarded so no combination of entries can return a blank, negative or invalid schedule.

Last reviewed . Methodology, editorial policy, report an error.